    25 October 2015, Volume 37 Issue 10
    Formal safety assessmenttechnology of hydraulic steel gate based on the set pair analysis
    HU Musheng1,SHENG Xujun2
    2015, 37(10):  1-4. 
    Asbtract ( 143 )  
    Related Articles | Metrics

    Abstract:When making a formal safety assessment of hydraulic steel gate, four indicators: structural strength,discharge capacity, water retaining capacity and service indicator are constructed as the assessment indicators system, and the weight of indicators is confirmed by experts using the analytic hierarchy process. Moreover, the grey relational analysis method is introduced to avoid the weight differences which are caused by subjective factors of experts and make the assessment more scientific and reasonable. For the uncertainty of formal safety assessment indicators of hydraulic steel gate, the set pair analysis is introduced, and a set pair analysis model for formal safety assessment of hydraulic steel gate is built by constructing a set pair of assessment indicators and assessment criteria. The calculation result of example verifies the effectiveness of set pair analysis forthe formal safety assessment of hydraulic steel gate.

    Design and application of ash conveying system for economizers of large and medium sized coal fired power plants
    SUN Jianchao
    2015, 37(10):  5-6. 
    Asbtract ( 178 )  
    Related Articles | Metrics

    Abstract:The economizer ash belongs to the type of gravity settling ash,which has features of large grain,large density and irregular shape,etc. This paper compared and analyzed different schemes of ash conveying system for economizers of large and medium sized coal fired power plants,summarized their merits,demerits and operation effects,and provided a reference for the design of ash conveying system.

    Application research on remote monitoring and diagnosis of excitation system for generator
    LI Yongzhong1, LI Fulong2, LI Xiaojun1, XU Yutao1, LI Song2
    2015, 37(10):  7-10. 
    Asbtract ( 189 )  
    Related Articles | Metrics

    Abstract:The general application of high capacity and high parameterized unit in the electrical power system brings up higher demands on the reliability of excitation system, thus it is very important to study on the application of remote monitoring and diagnosis of excitation system.Five modules have been studied according to key point of excitation system state monitoring:state monitoring and assess module,evaluation of excitation system exceptions and statistics of fault type module,evaluation of state monitoring of PID adjuster module, evaluation of state monitoring of PSS adjuster restraining low frequency oscillation module,evaluation of state monitoring of excitation regulator internal restriction and fixed value protection module.These studies have covered every aspect of excitation system and provided technical support to safety running and equipment maintenance.

    Analysis on auxiliary power saving methods of coal fired power plant
    TIAN Yanlong
    2015, 37(10):  11-14. 
    Asbtract ( 278 )  
    Related Articles | Metrics

    Abstract:Auxiliary power ratio is an important techno economic indicator of coal fired power plant.Taking the Inner Mongolia Datang
    International Tuoketuo Power Generation Company Limited as an example,this paper introduced the experience of auxiliary power saving methods from aspects of operation modes optimizing,energy saving and technical reconstruction,the advanced equipment management and the strict start
    stop controlling of units,etc.After that,this paper analyzed the negative effects of the implemented new environmental protection standard to auxiliary power ratio and proposed corresponding solutions.

    Analysis and governance of pipes sinking reason for reheat steam heat section
    LIU Ming,HE Guikuan,GAO Yang
    2015, 37(10):  15-16. 
    Asbtract ( 279 )  
    Related Articles | Metrics

    Abstract:A certain power plant found that a part of the reheat steam heat section of pipeline keep sinking.Site investigation and calculating check and analysis confirms that the main reason causing sinking pipes is that the actual mass of pipes exceeds design value.Meanwhile, property abnormality of constant support disc spring hangers at the site aggravate pipes sinking tendency. According to working characteristics of each bearing hangers,taking measures as replace constant hangers and increase output load of variable spring support and hanger can be effective solution of pipes sinking.

    Application for the mixing cols blast air technology of coal pulverizing systemin 330 MW coal fired boiler
    XU Jinhui1, MA Chuangang2,HAN Ling3
    2015, 37(10):  17-18. 
    Asbtract ( 240 )  
    Related Articles | Metrics

    Abstract:A certain power plant’s exhaust gas temperature of 330 MW boiler is much higher than designed.To lower the temperature,this paper brings up a retrofit scheme through mixing cold blast air technology of coal pulverizing system.This paper first introduces the principle of this technology and comparatively analyses it against low pressure economizer technology,then depicts the characteristics of mixing cold blast air technology,which are light wear,low investment,high quality of heat reclaims,etc.Matters that need attention are also discussed in the end if putting into operation.The exhaust gas temperature dropped 10~15℃ after transformation,which can be considered as remarkable effect of energy saving.

    Prevention and treatment of boilercoke extinguishing
    GUO Xiaofeng
    2015, 37(10):  19-21. 
    Asbtract ( 277 )  
    Related Articles | Metrics

    Abstract:This paper analyzed the influence factors of boiler coke forming and extinguishingin terms ofboiler design parameters,coals andcombustion mode,introduced the operation mode to improve the ability of boiler stable combustion and the coal blending method.After that, the prevention and treatment of boiler coke extinguishing was summarized.

    Application of MCS telemetry and automatic control system in pulverized coal milling system with intermediate storage bunker
    LIU Mingjie, REN Shangkun, HE Weiguo, LU Yongfu
    2015, 37(10):  22-24. 
    Asbtract ( 210 )  
    Related Articles | Metrics

    Abstract:This paper introduced the automatic controlfunction of pulverized coal milling system with intermediate storage bunker, which is realized by advanced raw coal level measurement technology to find out the optimum level of coal mill and control coal feeder,hot air gate and cold air gate automatically.This function could control system in the best condition by auto tracking optimumtechnology.

    Improvement of coal fired unit data collection system monitoring picture
    WANG Linlan1,CHEN Yuan2
    2015, 37(10):  25-26. 
    Asbtract ( 166 )  
    Related Articles | Metrics

    Abstract:For the full coverage,convenience and comfort of operation control system,the author analyzed problems existed in Xian Thermal Power Research Institute Company Limited unit No.2 data collection system software,and applied Shanghai Xinhua Control Technology (Group) Company Limiteds XDC800 system to reconfigure control logic.After reconfiguration,the reliability of system and friendliness of human machine interface was improved.These measures can be referred for reconstruction of similar units.

    Design improvement of 300 MW CFB boiler of Dongfang Boiler Group Company Limited
    WANG Zongren
    2015, 37(10):  27-29. 
    Asbtract ( 219 )  
    Related Articles | Metrics

    Abstract:The DG1025/17.4-II 18 circulating fluidized bed (CFB) boilerresearched and developed by Dongfang Boiler Group Company Limited has problems of inner heating surface abrasion,platen heating surface overheat,high exhaust gas temperature and high combustibles in fly ash. Fujian Huadian Yongan Power Plant Company Limitedhad improved the design of two units of 300 MW CFB boilers while construction,and solved aforesaid problems and increase the safety,economic efficiency,stability and reliability while operation.

    Analysis of booster pump diaphragm coupling fatigue failure
    GU Yong,WU Gang,YAN Zhe
    2015, 37(10):  30-31. 
    Asbtract ( 229 )  
    Related Articles | Metrics

    Abstract:This paper introduced the structure and working principle of diaphragm coupling,analyzed diaphragm stress distribution,fracture hazard area. After analyzing the reasons caused Huadian Jiangsu Energy Company Limited Jurong Power Plant’s booster pump diaphragm couplingfatigue failure.The author indicated that the center deviation is the main reason,and provided a serious of measures,such as to
    accomplish diaphragm coupling cold state center checking and adjustment,enhance inspection and etc.Safety of unit operation was ensured.

    Practical analysis on proportional mixed burning of coal slime
    ZENG Xianjiang,LIAN Chunqing,GUO Jun,YUAN Xiaoqiang,ZHANG Kaidong,MA Junjie
    2015, 37(10):  32-34. 
    Asbtract ( 206 )  
    Related Articles | Metrics

    Abstract:In this paper,a series of transform were carried out in the coal slime production and unloading system and the traditional coal conveying system.After that,the large proportional mixed burning was realized in the most economical way by using the old coal conveying
    system to transfer the coal slime,which made effective use of low calorific value coal slime,realized the comprehensive utilization of resources, reduced environmental pollution and improved the economic and social benefits.

    Frequent fault cause analysis and treatment for air intake switching valve of small size steam turbine in power plant
    WANG Hui, LI Yongjun
    2015, 37(10):  35-37. 
    Asbtract ( 248 )  
    Related Articles | Metrics

    Abstract:In a power plant,faults like valve automatically open,cut off valve not in place,oil leak and fire always happen in highpressure air intake switching valves of small size steam turbine since the 1000 MW unit was put into operation in 2010.These problems are solved effectively through such control methods as the corresponding upgrade of switching valve servomotor, cylinder oil inlet changing into dual control, and switching to the higher reliable servo valve.

    Frequent fault cause analysis and treatment for air intake switching valve of smallsize steam turbine in power plant
    WANG Hui, LI Yongjun
    2015, 37(10):  38-39. 
    Asbtract ( 324 )  
    Related Articles | Metrics

    Abstract:In a power plant,faults like valve automatically open,cutoff valve not in place,oil leak and fire always happen in high pressure air intake switching valves of small size steam turbine since the 1000 MW unit was put into operation in 2010.These problems are solved effectively through such control methods as the corresponding upgrade of switching valve servomotor,cylinder oil inlet changing into dual control,and switching to the higher reliable servo valve.

    Adjustments of 300 MW coal fired unit flue gas desulfurization system operation
    DAI Linzhong, ZHU Hui, LI Liguo, WU Jun
    2015, 37(10):  40-41. 
    Asbtract ( 189 )  
    Related Articles | Metrics

    Abstract:To lower operation cost,Yunnan Huadian Kunming Power Company Limited blended non designed coal into combustion, and allowed flue gas desulfurization (FGD) systemoperation deviated from design condition. In this case,SO2 emission cannot meet new national emission requirements.After analyzing effects of design coal type to desulfurization efficiency,the author made a serious of adjustments to FGD system based oncombusting non designed coal type.After adjustment,flue gas heat exchanger air leakage is lower than 1%,desulfurization efficiency is higher than 95%,and FGD system emission meets the new requirements under full load working condition.This also created good economy benefits to the company.

    Application of high pressure water washing on anair preheater of boiler
    ZHANG Guobin
    2015, 37(10):  42-44. 
    Asbtract ( 226 )  
    Related Articles | Metrics

    Abstract:The on line water washing technology for an air preheater has the advantages of low cost,easy operation,little influence on equipment,
    reducing the differential pressure of air preheater,preventing blockage etc.This paper took the No.3 generator unit of Huadian Weifang Power Generation Company Limited as an example, discussed the operation steps of high
    pressure water washing on air preheater and problems that should be noticed. After that, the experience of online water washing technology for air preheater is summarize.

    Case analysis on blade wear and breakage foradjustable static blade axial flow fan
    YANG Xiaogang
    2015, 37(10):  45-46. 
    Asbtract ( 226 )  
    Related Articles | Metrics

    Abstract:An analysis on the reasons of blade wear and breakage for the working adjustable static blade axial flow fan was carried out and correspondingsolutions were proposed from the aspects of debugging and running,maintenance and manufacturing of equipment.The solutions solved the problems efficiently and extended the performance life of blades,which insures the long time safe operation of coal fired power plants.

    Application of a tunable high intensity sonic sootblower on the No.1 air preheater of 600 MW power units
    FAN Guoqiang1, SUN Weiguo2, ZHU Junju2
    2015, 37(10):  47-50. 
    Asbtract ( 250 )  
    Related Articles | Metrics

    Abstract:Steam blowing technique is commonly used for traditionalsootblower of an air preheater,but it is less effective and its maintenance is more difficult.Moreover,a large amount of ammonium hydrogen sulfate is generated after the denitration system is put into operation, which exacerbates the ash blocking of air preheater and caused its lower heat transfer efficiency,higher current and resistance of flue gas side.
    For the ash blocking on the No.1 air preheater of Inner Mongolia Jinglong Power Generation Company Limited,the authors attempted to use
    a new type tunable high intensity sonic sootblower to solve the question and the soot blowing effect is improved obviously,the operation parameters of air preheater are also superior to that of a steam sootblower.This paper provided a new method and solved the problems of the poor effect of a steam sootblower and the blowing loss of heat exchanger components.

    Gas flow field analysisof the continuous emission monitoring system(CEMS)measuring point
    ZHAO Kai1,ZHANG Jinzhu2,YANG Pengfei3,SHEN Yuhui3
    2015, 37(10):  51-53. 
    Asbtract ( 220 )  
    Related Articles | Metrics

    Abstract:Since the front flue straight length of the outlet flue continuous emission monitoring system (CEMS) measuring point in unit 9 of Huadian Tianjin Junliangcheng Power Generation Company Limited does not meet the relative requirement in HJ/T 752007 Specifications for Continuous Emissions Monitoring of Flue Gas Emitted from Stationary Sources(On Trial),guide plate is installed at the elbow before CEMS measuring point as an optimized measure.The optimized numerical simulation results show that the section flue gas velocity at CEMS measuring point has a deviation of around 6.4% with the standard requirement (less than the standard deviation 7.0%),with a maximum value about 23m/s and a minimum value around 19m/s; while, the resistance of the entire flue only increases 9 Pa and the energy saving effect is good as well.Thus,this optimized measure enables the power plants with restricted site conditions to meet the environmental monitoring requirements.

    Reason analysis and treatment of high temperature of thrust bearing bush and oil for 600 MW large scale hydroelectric generating unit
    ZHANG Qi
    2015, 37(10):  54-57. 
    Asbtract ( 334 )  
    Related Articles | Metrics

    Abstract:The study analyzed phenomenon of high temperature of thrust bearing bush and oil for 600 MW large scale hydroelectric generating unit,found out reason which caused high temperature of bush and oil,and adopted main measure such as optimize oil circulation structure and increase oil circulation rate,and gained well result which can provide reference for same category unit to handle such kind of fault.

    Optimization and economic analysis of peak modulation methodologies for combined cycle unit of gas turbine
    XU Ming
    2015, 37(10):  58-59. 
    Asbtract ( 207 )  
    Related Articles | Metrics

    Abstract:This paper brings up an optimization of peak modulation methodologies for combined cycle unit of gas turbine according to its characteristics. It also comparatively analyses the peak modulation methodologies under low load operation and double shift operation.The result of this analysis is that double shift methodology achieves better economy but can also endangers the life span of combined cycle
    unit.

    Brief analysis of closed loop control for power grid engineering project budget
    ZHANG Wen, XIAO Xuemei, WANG Lei
    2015, 37(10):  60-62. 
    Asbtract ( 210 )  
    Related Articles | Metrics

    Abstract:For the past few years,State Grid has reinforced the management for execution schedule of engineering project investment plan.The method of statistics and assessment of investment plan complete status has been changed from imagery to financial affiliation.State Grid improved and perfected check mechanism for projects through arranging application service budget in the system by full chain management and control,thus real time query can be realized,and budget control for projects can be enhanced.Under the principle of unified management,professionalization and responsibility,and the aim of reinforcing application and real time control,primary units take full chain management and control as supplementary means to reinforce record of cost and build a system that is scientific,lean,intensive.

    Analysis and discussion on the technology of multipollutant removal in coal fired flue gases
    LI Weilin, SU Junhua, SHEN Yuhui, GU Jilin
    2015, 37(10):  63-64. 
    Asbtract ( 210 )  
    Related Articles | Metrics

    Abstract:The multi pollutant removal technology for coal fired flue gases and their present situation were introduced in this paper.The removal principles and the characteristics of sulfur oxides,nitrogen oxides and Hg in coal fired flue gases were described in this paper.The technology of multi pollutant removal from the coal fried flue gases is an effective way to the combined control of the multi pollutant of the coal fired boiler in the future.

    Modification scheme comparison of ultra lowfluegas emission in 600 MW coal fired generating unit
    ZHANG Xuehai1,JIA Zhaopeng2
    2015, 37(10):  65-68. 
    Asbtract ( 293 )  
    Related Articles | Metrics

    Abstract:2×600MW coal fired generating unit of Huaneng Tongchuan Zhaojin Power Plant phase 1 starts to have modification for flue gas emission in order to make sure to meet standard for ultra low discharge of pollutants.This paper brought up two plans and analyzed them through investment,economy,construction period,construction difficulties,environment and other factors.One is low temperature economizer plus wet chimney modification,the other one is MGGH plus dry chimney modification,which is recommended after an integrated assessment.

    Comparative researches on the heat transfer characteristics of the SG between AP1000 and 2rd generation nuclear power plant
    LI Yu1,2,ZHOU Tao1,2,LIU Liang1,2,FANG Xiaolu1,2
    2015, 37(10):  69-71. 
    Asbtract ( 240 )  
    Related Articles | Metrics

    Abstract:By calculating the thermal resistance of the primary loop,the secondaryloopthe tube wall,the fouling resistance,the heat transfer coefficient ofsteam generators for AP1000,the Daya Bay Nuclear Power Plant and Qinshan Nuclear Power Plantare calculatedand the results are analyzed by comparing with each other.The data shows thatthe heat transfer coefficient of the AP1000 steam generator is 8978W/(m2·℃), which is slightly larger than that of the Daya Bays and Qinshans.Meanwhilethe secondary loop of AP1000 SG has the minimum thermal resistance of the three,but the thermal resistance of the primary loop,fouling resistance and thermal resistance values of the wall tube are
    basically equal to those of Daya Bay,and both are superior to the corresponding values of Qinshan.The heat resistance of the tube wall account for more than 50% of the general heat resistance.Overall,the designs of each part of AP1000 steam generator are more reasonable
    compared to the second generation of the steam generatorwhich improves its heat transfer characteristics.

    Application of wireless data transceiver technology in wind farm supervisory control and data acquisition (SCADA) systems
    HUANG Chunli, GAO Min, GAO Jinming
    2015, 37(10):  72-75. 
    Asbtract ( 159 )  
    Related Articles | Metrics

    Abstract:On the basis of wireless data transceiver, a new wireless transmission technology is proposed to solve problems such as the long fiber construction cycle of traditional fiber transmission in wind farm and the inconveniences that might be brought by fiber fault maintenance.This paper analyzes the differences,advantages and disadvantages between traditional wireless transmission technology and the new one.It also presents the structure and essentials of supervisory control and data acquisition (SCADA) systems and wireless data transceiver technology.
    Based on the studies,the single wind turbine wireless transmission network system is set up and applied in a wind farm SCADA systems.The result shows SCADA system status data can be received and sent through a stable,reliable,real
    time and accurate data transmission.