The process and features of startup through intermediate pressure(IP)cylinder of two 600MW units in some power plant project phase I were presented.The faults occurred in the process of startup through IP cylinder were analyzed in detail, and the relevant treatment measures were proposed. At last, it was pointed out that the tartup through IP cylinder is a safer and more economic way for unit startup.